TITLE
20 ENVIRONMENTAL PROTECTION
CHAPTER 5 PETROLEUM
STORAGE TANKS
PART 110 GENERAL
OPERATING REQUIREMENTS FOR ABOVE GROUND STORAGE TANK
SYSTEMS
20.5.110.1 ISSUING AGENCY: New
Mexico Environmental Improvement Board.
[20.5.110.1 NMAC - N,
07/24/2018]
20.5.110.2 SCOPE: This part applies to owners and operators of above ground
storage tanks as provided in 20.5.101 NMAC. If the owner and operator of a
storage tank are separate persons, only one person is required to comply with
the requirements of this part, including any notice and reporting requirements;
however, both parties are liable in the event of noncompliance.
[20.5.110.2 NMAC - N,
07/24/2018]
20.5.110.3 STATUTORY AUTHORITY: This part is
promulgated pursuant to the provisions of the Hazardous Waste Act, Sections
74-4-1 through 74-4-14 NMSA 1978, and the general provisions of the
Environmental Improvement Act, Sections 74-1-1 through 74-1-17 NMSA 1978.
[20.5.110.3 NMAC - N, 07/24/2018]
20.5.110.4 DURATION: Permanent.
[20.5.110.4 NMAC - N,
07/24/2018]
20.5.110.5 EFFECTIVE
DATE: July 24, 2018 unless a later date
is indicated
in the bracketed
history note at the end
of a section.
[20.5.110.5 NMAC - N,
07/24/2018]
20.5.110.6 OBJECTIVE: The purpose of 20.5.110 NMAC is to ensure that the operation
and maintenance of above ground storage tanks will prevent releases and to
protect the public health, safety and welfare and the environment of the state.
[20.5.110.6 NMAC - N, 07/24/2018]
20.5.110.7 DEFINITIONS: The
definitions in 20.5.101 NMAC apply to this part.
[20.5.110.7 NMAC - N,
07/24/2018]
20.5.110.8 to 20.5.110.999 [RESERVED]
20.5.110.1000 OPERATION AND MAINTENANCE OF ABOVE GROUND STORAGE TANK SYSTEMS: Owners and operators
shall properly maintain all tanks, piping, secondary containment and other
associated equipment required in 20.5.109 NMAC, and shall ensure that all
tanks, piping, secondary containment and other associated equipment for all
storage tank systems are fully operational at all times. Owners and operators shall notify the
department in accordance with 20.5.118 NMAC if a visual inspection, other
inspection or testing conducted in accordance with 20.5.110 NMAC or 20.5.111
NMAC indicates that a release may have occurred.
A. Owners and operators shall visually inspect monthly an AST and all its components
that are readily accessible
to visual inspection.
B. Owners and operators
shall maintain the exterior coating of an AST and ancillary equipment not in contact
with soil in accordance with the current edition of an industry standard or
code of practice developed by a nationally recognized association or
independent testing laboratory approved in advance by the department. The following may be used to comply with this
requirement:
(1) Society of
Protective Coatings SSPC-PA 1, “Shop, Field, and Maintenance Painting of Steel”;
(2) Society of
Protective Coatings, “The Inspection of Coatings and Linings: A Handbook of
Basic Practice for Inspectors, Owners and Specifiers”;
(3) Society of
Protective Coatings
SSPC-PA Guide 4, “Guide to
Maintenance Repainting with Oil
Base or Alkyd Painting Systems”;
or
(4) Society of
Protective Coatings SSPC-PA Guide 5, “Guide to Maintenance Coating of Steel
Structures in Atmospheric Service”.
C. Owners and operators
shall mark fill port lids and label the tanks of ASTs as to the regulated
substance stored in accordance with the current edition of an industry standard
or code of practice developed by a nationally recognized association or
independent testing laboratory approved in advance by the department. The following shall be used to comply with
this requirement: American Petroleum Institute RP 1637, “Using the API Color-Symbol
System to Mark Equipment and Vehicles for Product Identification at Gasoline
Dispensing Facilities and Distribution Terminals”.
D. If any steel
piping installed in a trench is used in an AST system, owners and operators
shall visually inspect the trench monthly.
Owners and operators shall draw off any liquid that has accumulated in
the trench within one week of the accumulation, and shall remove any other
debris that has accumulated inside the trench.
Owners and operators shall properly treat and dispose of any accumulated
liquid with a visible sheen and the disposal shall be in accordance with all
federal, state, and local statutes, ordinances, and regulations. If a basin sump is located in the trench,
owners and operators shall keep the basin sump free of accumulated liquid and
debris. Owners and operators shall not
install any valves in any basin sump in a piping trench.
E. Owners and operators
shall check ASTs monthly for the
presence of any accumulated liquids, other than the intended regulated
substance. ASTs shall be checked at
the lowest possible point inside
the tank. Any accumulated liquid other than the intended regulated substance shall be removed to the
extent technically possible. Owners
and operators shall properly dispose
of any liquid removed from an AST.
[20.5.110.1000 NMAC - N,
07/24/2018]
20.5.110.1001 OPERATIONS AND MAINTENANCE PLAN: Owners and operators
of all storage tank systems shall adopt and implement a written operations and
maintenance plan, which they shall keep at the facility for the life of the
storage tank system. Owners and
operators of unmanned storage tank systems may keep the operations and
maintenance plan at an alternate location as long as it is made readily
available to the department upon request.
The operations and maintenance plan shall be as specific as possible for
each facility and shall include the piping and ancillary equipment that
routinely contains regulated substances, or controls the flow of regulated
substances. Owners and operators shall
use, by reference, operational and maintenance guidance from the current
edition of an industry standard or code of practice developed by a nationally
recognized association or independent testing laboratory. Owners and operators who reference a current
edition of an industry standard or code of practice shall maintain a copy of
the code or standard they reference.
Owners and operators shall not implement the plan until it has been
approved by the department.
A. At a minimum, the operations and maintenance
plan shall include the following:
(1) a detailed plan showing inspections,
operations, testing and maintenance to be done on a daily, monthly, quarterly
and annual basis; the plan shall include a description of how owners and
operators properly dispose of regulated substances spilled at the facility, and
any water or soil removed from any part of the storage tank system where there
is any indication it might be or have been contaminated with a regulated
substance;
(2) a
description of periodic operation and maintenance walk-through inspections in
accordance with 20.5.110.1008 NMAC; and
(3) responses
to emergency situations; this information shall be readily accessible at the facility;
responses to emergency situations shall include the following:
(a) the
location of equipment to be shut down during an emergency and how to safely
perform these tasks;
(b) actions
to be taken in the event of a fire, flooding, a spill, or a release of
regulated substances;
(c) a
site diagram; and
(d) a
list of whom to notify or call during or after an emergency situation.
B. Owners and
operators shall use one or more of the following to
comply with the requirements
of this
section:
(1) American Petroleum Institute 570, “Piping Inspection Code: In-Service
Inspection, Repair, and Alteration Piping Systems”;
(2) American Petroleum Institute
Standard 653, “Tank Inspection, Repair, Alteration, and Reconstruction”; or
(3) Steel Tank
Institute Standard SP001, “Standard for Inspection of In-Service Shop
Fabricated Aboveground Tanks for Storage of Combustible and Flammable Liquids”; or
C. Owners and operators may
submit to the department for approval an alternate plan which contains all the
information requested in this section.
D. Owners and operators of
storage tank systems that have been placed in temporary closure in compliance
with 20.5.115.1501 NMAC shall not be required to have an operations and
maintenance plan, unless one or both of the following conditions is present:
(1) the
storage
tank contains greater than one inch of regulated substance; or
(2) the storage tank system
has steel components that are in contact with an electrolyte, such as soil,
water or concrete.
[20.5.110.1001 NMAC - N,
07/24/2018]
20.5.110.1002 OPERATION,
MAINTENANCE, REPAIR AND REPLACEMENT OF
SECONDARY CONTAINMENT FOR ASTS:
A. Owners and operators shall operate, maintain and
repair secondary containment in accordance with the current edition of an industry
standard or code of practice developed by a nationally recognized association
or independent testing laboratory approved in advance by the department.
B. Owners and operators shall not store inside the
secondary containment any material which is chemically reactive with the
regulated substance stored in the AST system, or with the AST itself. Owners and operators shall not store any
material in the secondary containment that reduces the capacity of the secondary
containment below the requirements in 20.5.109.904 NMAC.
C. Owners and operators shall draw off any
accumulation of liquid in the secondary containment, including all sumps,
within one week of the accumulation, and shall remove any other debris that has
accumulated inside the secondary containment.
Owners and operators shall properly treat and dispose of any accumulated
liquid with a visible sheen. If gravity
drain valves are used to remove the accumulated liquid from the secondary
containment, owners and operators shall keep all valves closed except during
the process of draining the accumulated liquid.
D. In order
to maintain the highest level of secondary containment in case of a discharge
from, or an overfill of, an AST system, owners and operators shall keep the
spill containment buckets, catchment basins, containment sumps, basin sumps,
and piping trenches free of water, regulated substances and debris.
E. Owners and operators shall, in accordance
with the current edition
of an industry standard or code of practice developed by a nationally recognized
association or independent testing laboratory approved in advance by
the department:
(1) maintain,
repair and replace any concrete secondary containment
systems; and
(2) repair
all significant cracks in
the floors and walls of concrete secondary
containment systems.
F. Owners and
operators shall use one or more of the following
to comply with the concrete secondary containment system repair requirements in
Subsection E above:
(1) Society of
Protective Coating and National Association of
Corrosion Experts SSPC-TU2/NACE 6G197,
“Design, Installation and Maintenance of
Coating Systems for Concrete used in
Secondary Containment’;
(2) American Concrete
Institute 224R, “Control of
Cracking in Concrete Structures”; or
(3) American Concrete
Institute “Concrete Repair Manual”.
G. Owners and operators
shall maintain, repair and replace
any geo-synthetic liner according to manufacturer’s
instructions, which owners and operators shall keep readily available
at the
facility for the life of
the
liner.
H. Owners and operators shall protect from corrosion any
secondary containment constructed of
steel, and shall
cathodically protect any portion
of the
steel secondary containment that is in contact with
an electrolyte, including soil or water.
Owners and operators shall maintain the exterior of any steel secondary
containment in accordance with the current edition of an industry standard or
code of practice developed by a nationally recognized association or
independent testing laboratory approved in advance by the department. The following shall be used to comply with
this requirement: Society of Protective
Coatings SSPC-PA-1, “Shop, Field, and Maintenance Painting of Steel”.
I. Owners and operators of above ground storage
tanks which are either double-walled or which have an interstitial space that
is monitored as a method of release detection shall comply with the following
applicable requirements:
(1) where
design and release detection method allow the interstice of a double-walled
above ground storage tank to be visually inspected without disturbance of the
release detection system, owners and operators shall monthly visually inspect
for the presence of water, regulated substances or debris;
(2) if testing conducted in accordance with
20.5.109, 20.5.110 or 20.5.111 NMAC indicates that the stored regulated
substance is leaking into the interstice of the AST, then owners and operators
shall have the tank repaired in accordance with the tank manufacturer’s
instructions or specifications, or with the current edition of an industry
standard or code of practice developed by a nationally recognized association
or independent testing laboratory. Also,
owners and operators shall ensure the repair is conducted in accordance with
the requirements in 20.5.110.1010 NMAC;
(3) owners and operators shall monitor all
vertical ASTs with an interstitial
space between the tank bottom and secondary containment
for the presence
of water or regulated substances; if gravity
drain valves are used for monitoring and
removal of water or regulated substances, owners and operators shall keep
them closed except during the
process of monitoring and draining;
(4) owners and operators shall keep all sumps associated with interstitial monitoring free
of
water;
(5) owners and operators shall
annually inspect and test all sensors used to monitor interstitial spaces, in
accordance with manufacturer’s testing protocol, or in accordance with the
current edition of an industry standard or code of practice developed by a
nationally recognized association or independent testing laboratory approved in
advance by the department; and
(6) owners and operators shall
remove any liquid found in interstitial spaces, and dispose of it
properly.
J. Owners and operators
shall operate, maintain, and repair containment sumps on AST systems in order
to prevent any leaks or spills in the containment area from entering the
environment.
K. Under-dispenser containment must allow for visual
inspection and access to the components in the containment system or be
periodically monitored for liquid in the sump in accordance with 20.5.110.1008
NMAC.
L. Containment sumps shall be maintained to meet
requirements in 20.5.110.1007 NMAC.
[20.5.110.1002 NMAC - N,
07/24/2018]
20.5.110.1003 OPERATION, REPAIR, AND MAINTENANCE OF
VAULTS:
A. Owners and operators
shall operate, maintain and repair the walls and floor of a vault in accordance
with the current edition of an industry standard or code of practice developed
by a nationally recognized association or independent testing laboratory
approved in advance by the department.
Owners and operators shall use one or more of the following to comply
with the requirements of this section:
(1) Society of Protective
Coating and National Association of Corrosion Experts SSPC-TU2/NACE 6G197,
“Design, Installation and Maintenance of Coating Systems for Concrete Used in
Secondary Containment”;
(2) American
Concrete
Institute 224R, “Control of Cracking in Concrete Structures”; or
(3) American
Concrete
Institute, “Concrete Repair Manual”.
B. Owners and operators
shall visually inspect the interior of any vault from the outside monthly, and
annually shall enter and inspect the interior of the vault. Owners and operators shall draw off any
liquid that has accumulated in a vault within one week of any accumulation of
liquid if the liquid is in contact with the tank or piping (but need not draw
off liquid only in contact with a tank’s saddles, skid or other support), and
shall remove any other debris that has accumulated inside the vault and which
is in contact with the tank, piping or saddle, skid or other support. Owners and operators shall properly treat and
dispose of any accumulated liquid with a visible sheen and the disposal shall
be in accordance with all federal, state, and local statutes, ordinances, and
regulations. If a sump is located in the
vault, owners and operators shall keep the liquid trap free of water and
debris. Owners and operators shall not
install any valves in any sump in a vault.
C. Owners and operators shall
not store inside a vault any material which is chemically reactive with the
regulated substance stored in the AST system, or with the AST itself.
D. Owners and operators
shall ensure that a vault is well vented before any fuel transfer begins, and
shall keep open all vents during the transfer.
E. For vaults with roofs,
owners and operators shall properly maintain and repair the roof of a vault in
accordance with the current edition of an industry standard or code of practice
developed by a nationally recognized association or independent testing
laboratory approved in advance by the department.
[20.5.110.1003 NMAC - N,
07/24/2018]
20.5.110.1004 OPERATION, REPAIR, AND MAINTENANCE OF VENTING SYSTEMS: Owners and operators shall operate, maintain and repair
venting systems in accordance with the current edition of an industry standard
or code of practice developed by a nationally recognized association or
independent testing laboratory approved in advance by the department. At least monthly, owners and operators shall
check emergency vents to ensure they are operational. The following shall be used to comply with
this requirement: National Fire
Protection Association Standard 91, “Standard for Exhaust Systems for Air
Conveying of Vapors, Gases, Mists, and Noncombustible Particulate Solids”.
[20.5.110.1004 NMAC - N,
07/24/2018]
20.5.110.1005 OPERATION AND MAINTENANCE OF SPILL AND OVERFILL PREVENTION: Owners
and operators shall ensure that releases due to spilling or overfilling do not
occur.
A. Owners and operators shall ensure that the volume available in a tank is greater than the volume of product to be transferred to the tank before the transfer is made and that the transfer operation is monitored constantly to prevent overfilling and spilling. Owners and operators shall comply with the transfer procedures described in the current edition of an industry standard or code of practice developed by a nationally recognized association or independent testing laboratory approved in advance by the department. Owners and operators shall use one or more of the following to comply with this requirement:
(1) National
Fire Protection Association Standard 30A, “Code for Motor Fuel Dispensing
Facilities and Repair Garages”;
(2) International
Code Council, “International Fire Code”;
(3) Petroleum Equipment Institute Publication
RP600, “Recommended Practices for Overfill Prevention for Shop-Fabricated Above
Ground Tanks”; or
(4) American Petroleum Institute Standard 2350,
“Overfill Protection for Storage Tanks in Petroleum Facilities”.
B. For additional guidance on Subsection A, see the
following:
(1) National
Fire Protection Association Standard 385, “Standard for Tank Vehicles for
Flammable and Combustible Liquids”;
(2) American
Petroleum Institute Recommended Practice 1007, “Loading and Unloading of MC
306/DOT 406 Cargo Tank Motor Vehicles”;
(3) American
Petroleum Institute Publication 1621, “Bulk Liquid Stock Control at Retail
Outlets”; or
(4) National
Fire Protection Association Standard 30, “Flammable and Combustible Liquids
Codes”.
C. Owners and operators
of AST systems shall ensure that spill prevention equipment required in
20.5.109.910 NMAC is liquid tight, maintained, and fully operational at all
times. In order to ensure the equipment
meets these requirements, owners and operators shall no later than three years
after the effective date of these regulations meet the following requirements:
(1) Spill
prevention equipment installed where the outer and inner walls along with
bottom of the equipment are clearly visible shall be either monitored monthly
or tested every three years. A liquid,
pressure, or vacuum test method shall be used in accordance with one of the following:
(a) the
equipment manufacturer’s developed and published testing
requirements;
(b) Petroleum Equipment Institute RP 1200,
“Recommended Practices for the Testing and Verification of Spill, Overfill,
Leak Detection, and Secondary Containment Equipment at UST Facilities”;
or
(c) the current
edition of another industry standard or code of practice developed by a
nationally recognized association or independent testing laboratory approved in
advance by the department.
(2) Spill
prevention equipment installed where the outer walls and the bottom are not
visible shall be tested by a liquid, pressure, or vacuum test method every
three years in accordance with one of the documents in Paragraph (1) of this
subsection.
(3) Factory
installed spill prevention equipment installed as an integral component of a
double walled storage tank system shall either be tested every three years in
accordance with Paragraph (1) of this subsection or, where a leak in the spill
prevention equipment can be detected in the interstice of the tank, owners and
operators shall monitor the interstice of the tank every 30 days.
(4) Spill prevention equipment that either
fails when tested or is found to be damaged during monthly monitoring shall be
repaired or replaced in accordance with 20.5.110.1010 NMAC.
(5) A
report shall be produced which includes the results of any vacuum, pressure, or
liquid testing conducted on spill prevention equipment and the report shall be
submitted to the department in accordance with the requirements in
20.5.110.1016 NMAC and maintained in accordance with the requirements in
20.5.110.1015 NMAC.
(6) Records
of the monthly monitoring and testing required in this subsection shall be
maintained in accordance with 20.5.110.1015 NMAC.
D. Owners and
operators of AST systems shall ensure that overfill prevention equipment
required in 20.5.109.910 NMAC is maintained and fully operational at all
times. In order to ensure the equipment
meets these requirements, owners and operators shall, no later than three years
after the effective date of these regulations, and every three years thereafter
have the overfill prevention equipment inspected or tested and shall meet the
following:
(1) The
inspection shall verify the equipment meets the requirements in 20.5.109.910
NMAC, and if the equipment fails to meet these requirements, it shall be
repaired, replaced, or re-installed. The
repair, replacement, or re-installation shall be in accordance with the
manufacturer’s instructions or the current edition of an
industry standard or code of practice developed by a nationally recognized
association or independent testing laboratory approved in advance by the
department;
(2) Drop
tube style overfill prevention equipment shall be removed from the tank for the
inspection;
(3) Owners
and operators shall ensure the inspections or tests are performed in accordance
with the methods and procedures listed in one of the following:
(a) Petroleum Equipment Institute RP 1200, “Recommended
Practices for the Testing and Verification of Spill, Overfill, Leak Detection,
and Secondary Containment Equipment at UST Facilities”, or
(b) testing
requirements developed and published by the overfill prevention equipment
manufacturer;
(4) If
more than one type of overfill prevention equipment is installed on an AST,
owners and operators shall ensure that none of them will interfere with the
proper operation of any of the others; and
(5) A
report shall be produced which includes the results of any inspections or
testing conducted on overfill prevention equipment and the report shall be
submitted to the department in accordance with the requirements in
20.5.110.1016 NMAC and maintained in accordance with the requirements in
20.5.110.1015 NMAC.
E. Owners and operators shall report, investigate, and clean
up any spills and overfills in accordance with 20.5.118 NMAC.
F. Owners and operators
of a storage tank system that meets the requirements for temporary closure and
the tank is empty as defined in 20.5.115.1501 NMAC shall not be required to
periodically test the spill and overfill prevention equipment.
G. Owners
and operators of storage tank systems shall ensure tests of all spill and
overfill prevention equipment as required in this section are performed by a
qualified tester. The requirements for
testers can be found in 20.5.105 NMAC.
[20.5.110.1005 NMAC - N, 07/24/2018]
20.5.110.1006 OPERATION AND MAINTENANCE OF CORROSION PROTECTION: Owners and operators of metal storage tank
systems with any metal tank or piping with corrosion protection shall comply with
the following requirements to ensure that releases due to corrosion are
prevented until the storage tank system is permanently closed or undergoes a
change in service pursuant to 20.5.115 NMAC.
A. Owners and operators shall operate and maintain corrosion
protection systems to continuously provide corrosion protection to all metal
components of the system that routinely contain regulated substances and are in
contact with an electrolyte, to include soil or water. Owners and operators shall operate and
maintain corrosion protection systems in accordance with the current edition of
an industry standard or code of practice developed by a nationally recognized
association or independent testing laboratory approved in advance by the
department. Owners and operators shall
use one or more of the following to comply with the requirements of this
section:
(1) American
Petroleum Institute Publication 651, “Cathodic Protection of Aboveground
Petroleum Storage Tanks”;
(2) American
Petroleum Institute Publication 652, “Linings of Aboveground Petroleum Storage
Tank Bottoms”;
(3) American
Petroleum Institute Publication 1632, “Cathodic Protection of Underground
Petroleum Storage Tanks and Piping Systems”
(4) National
Association of Corrosion Engineers Publication RP0193, “External Cathodic
Protection of On-Grade Carbon Steel Storage Tank Bottoms”;
(5) National
Association of Corrosion Engineers Publication SP0169, “Standard Practice for
Control of External Corrosion on Underground or Submerged Metallic Piping
Systems”.
B. Owners and operators shall ensure that all storage tank
systems equipped with cathodic protection are inspected for proper operation by
a qualified corrosion expert in accordance with the following requirements:
(1) Frequency: owners and operators shall test all cathodic
protection systems as follows:
(a) within
six months of installation and at least every three years thereafter;
(b) within
six months of a modification or repair; or
(c) another
reasonable time frame approved in advance in writing by the department;
(2) Inspection criteria: the criteria that are used to determine that
cathodic protection is adequate as required by this section must be in
accordance with the current edition of an industry standard or code of practice
developed by a nationally recognized association or independent testing
laboratory approved in advance by the department;
(3) Owners and operators of storage tank systems shall provide the department a report on the
cathodic protection system test that includes the following:
(a) name
of facility, facility address, and facility ID number issued by the department;
(b) name
of the technician who performed the test;
(c) certification
of the technician in the type of test performed, including certification
numbers, national association where the certification was obtained, and
expiration date of the certification;
(d) description
of cathodic protection system, for example impressed current, galvanic;
(e) description
of storage tank system including tank ID number, product, capacity, tank type,
piping, flex connectors;
(f) type
of test conducted, such as: routine three-year test; test within six months of
installation; test within six months after repair or modification;
(g) whether
all flex connectors or metal risers that routinely contain a regulated
substance and are in contact with an electrolyte are protected from
corrosion. If isolation boots, jackets,
or other non-corrodible materials are used to protect this equipment from corrosion,
it shall be determined if they are still providing protection from corrosion.
(h) tester’s
pass/fail evaluation and actions to be taken after evaluation;
(i) facility
drawing of the storage tank system and cathodic protection system, indicating
location of test points on the storage tank system, cathodic protection test
stations, and reference electrode placement; and
(j) description
of cathodic protection system repair or modification.
(4) Owners
and operators of storage tank systems shall provide the department a report on
impressed current systems that includes all requirements listed in
20.5.110.1016 NMAC; and
(a) rectifier
manufacturer, model, serial number, rated direct current output voltage and
amperage;
(b) rectifier
tap settings, direct current output voltage and amperage, and hour meter
reading;
(c) description
of structure tested, contact point of test lead, and reference electrode
placement;
(d) structure
to soil potential with current applied in millivolts;
(e) structure
to soil potential with current interrupted, instant OFF in millivolts;
(f) 100
millivolts polarization shift, end voltage and voltage change; and
(g) test
results.
(5) Owners
and operators of storage tank systems shall provide the department a report on
galvanic systems that includes all requirements listed in 20.5.110.1016 NMAC;
and
(a) description
of structure tested, contact point of test lead, and reference electrode
placement;
(b) structure
to soil potential measured locally in millivolts;
(c) structure
to soil potential measured remotely in millivolts; and
(d) test
results.
(6) Owners and operators shall use one or
more of the following to comply with the requirements of this section:
(a) National
Fire Protection Association Standard 30, “Flammable and Combustible Liquids
Code”;
(b) National Fire Protection Association
Standard 30A “Code for Motor Fuel Dispensing Facilities and Repair Garages”;
(c) American Petroleum Institute Publication RP
1615, “Installation of Underground Petroleum Storage Systems”;
(d) American Petroleum Institute Publication RP
1632, “Cathodic Protection of Underground Petroleum Storage Tanks and Piping
Systems”;
(e) International Code Council,
"International Fire Code";
(f) NACE
International Test Method TM 0101, “Measurement Techniques Related to Criteria
for Cathodic Protection of Underground Storage Tank Systems”;
(g) NACE
International Test Method TM0497, “Measurement Techniques Related to Criteria
for Cathodic Protection on Underground or Submerged Metallic Piping Systems”;
(h) Steel
Tank Institute Recommended Practice R051, “Cathodic Protection Testing
Procedures for STI-P3® USTs”;
(i) NACE
International Standard Practice SP 0285, “External Control of Underground
Storage Tank Systems by Cathodic Protection”; or
(j) NACE
International Standard Practice SP 0169, “Control of External Corrosion on
Underground or Submerged Metallic Piping Systems”.
C. Owners and operators shall inspect storage tank systems
with impressed current cathodic protection systems every 60 days to ensure the
equipment is running properly. Owners
and operators shall record the date, time, readings and results of each
inspection in a log kept at the facility, and indicate who performed each
inspection.
D. Owners and operators shall monthly inspect any equipment
or materials used to isolate metal components of AST systems and shall repair
or replace equipment and materials used to meet corrosion protection
requirements in this section.
E. For storage tank systems using cathodic protection,
owners and operators shall maintain records of the operation of the cathodic
protection in accordance with 20.5.110.1015 NMAC to demonstrate compliance with
the performance standards in this section.
These records shall provide the following:
(1) the results of the last three
inspections required in Subsection C of this section; and
(2) the results of testing from the last
two inspections required in Subsection B of this section.
[20.5.110.1006 NMAC - N,
07/24/2018]
[The department provides an
optional form that may be used for the cathodic protection system test report
required in Subsection B. The form is
available on the petroleum storage tank bureau’s pages on the department
website, or by contacting the Petroleum Storage Tank Bureau at 505-476-4397 or
2905 Rodeo Park Drive East, Building 1, Santa Fe, New Mexico 87505.]
20.5.110.1007 OPERATION AND
MAINTENANCE OF CONTAINMENT SUMPS FOR AST SYSTEMS:
A. Owners
and operators shall maintain
all containment sumps (including but not limited to under
dispenser sumps and transition sumps) and draw
off liquid that has accumulated in the containment sumps within
one week of the accumulation, and
shall remove any other debris
that has accumulated inside the
containment sumps. Owners
and operators shall properly treat and dispose
of any accumulated liquid with a visible
sheen, and the disposal shall be in
accordance with all federal, state, and local statutes, ordinances, and
regulations. If
gravity drain valves are used to remove
accumulated liquid from the
containment sumps, owners and operators
shall keep all valves closed except during the process of draining the
accumulated liquid.
B. In order to
maintain the highest level of secondary containment in case of a discharge
from, or an overfill of, an AST system, owners and operators shall keep the
containment sumps and basin sumps free of water, regulated substances, and
debris.
C. Owners and
operators shall maintain all containment sumps associated with interstitial
monitoring of underground piping; the sumps shall be liquid tight and kept free
of water.
D. Owners and
operators of AST systems with single walled containment sumps associated with
interstitial monitoring shall have the integrity of the sumps tested no later
than three years after the effective date of these regulations, and every three
years thereafter, in accordance with the following:
(1) Hydrostatic
or other test methods shall be conducted to ensure the containment sumps are
liquid tight including at all penetrations in accordance
with one of the following:
(a) the equipment manufacturer’s
developed and published testing requirements;
(b) Petroleum Equipment Institute RP 1200, “Recommended
Practices for the Testing and Verification of Spill, Overfill, Leak Detection,
and Secondary Containment Equipment at UST Facilities”; or
(c) the
current edition of an industry standard or code of practice developed by a
nationally recognized association or independent testing laboratory approved in
advance by the department;
(2) Hydrostatic test
methods using a test apparatus developed specifically for testing containment
sumps shall ensure the containment sumps are liquid tight including at all
penetrations and comply with one of the following:
(a) protocols
developed by the manufacturer of the test apparatus and the certification as
listed on the web site of the national work group on leak detection evaluation;
(b) protocols
developed and published by the manufacturer of the containment sump;
(c) Petroleum Equipment Institute RP 1200,
“Recommended Practices for the Testing and Verification of Spill, Overfill,
Leak Detection, and Secondary Containment Equipment at UST Facilities”; or
(d) an
alternate test method approved by the department in writing in advance in
accordance with the requirements for Alternate Methods Requests in
20.5.110.1014 NMAC.
(3) A
low liquid level hydrostatic test method may be conducted if all of the following
conditions are met:
(a) test
method used shall be in accordance with the following:
(i) the
liquid level meets the third-party certification for the sensor installed in
the sump;
(ii) the
duration of the test shall be a minimum of one hour unless a different test
period is specified by the containment sump manufacturer or in (iii) below;
(iii) the
current edition of an industry standard or code of
practice developed by a nationally recognized association or independent
testing laboratory approved in advance by the department;
(b) either
a hydrostatic test shall be conducted every 12 years in accordance with
Paragraph (1) and (2) of Subsection D or a site check shall be conducted every
12 years in accordance with in Subsection B of 20.5.118.1801 NMAC.
(c) a
sump sensor that automatically shuts off equipment associated with the sump and
meets the requirements for placement and testing of sensors used for
interstitial monitoring in Subparagraph (b) of
Paragraph (3) of Subsection A of 20.5.111.1106 NMAC;
(4) A
low liquid level test per Paragraph (3) of this subsection shall not be
conducted if the following conditions exist:
(a) a
liquid is discovered in the sump or evidence is found that a liquid has been at
a level equal to or higher than the lowest penetration in the sump; then
testing has to be conducted in accordance with Paragraph (1) of this
subsection;
(b) sensors
in containment sumps are discovered to be located higher than the lowest part
of the sump; then a test shall be conducted in accordance with Paragraph (1) of
this subsection and owners and operators shall report and investigate a
suspected release in accordance with the requirements in 20.5.118 NMAC; or
(c) a
site check conducted in accordance with Paragraph (3) of this subsection
indicates there has been a release from the containment sump.
E. Owners and
operators of AST systems with double-walled containment sumps associated with
interstitial monitoring shall have the integrity of the sumps tested no later
than three years from the effective date of these regulations, and every three
years thereafter, in accordance with one of the following:
(1) interstices
under vacuum, pressure, or brine filled, are continuously monitored by use of
interstitial sensors or visually inspected every 30 days, and the monitoring
records are maintained in accordance with 20.5.110.1015 NMAC. Owners and operators shall ensure that annual
functionality testing or annual inspections of the monitoring equipment are
conducted in accordance with 20.5.111.1104 NMAC. Owners and operators who cannot demonstrate
that the interstices of the containment sumps are continuously monitored or
inspected every 30 days shall have the sumps tested in accordance with
Subsection D above; or
(2) containment
sumps with dry interstices that are not continuously monitored are integrity
tested in accordance with Subsection D of 20.5.110.1007 NMAC.
F. All sensors and
equipment used to monitor containment sumps and their interstices shall be
functionality tested annually in accordance with 20.5.111.1104 NMAC.
G. A
report shall be produced which includes the results of the testing, and the
report shall be submitted in accordance with 20.5.110.1016 NMAC and maintained
in accordance with the requirements in 20.5.110.1015 NMAC.
H. Owners
and operators of storage tank systems shall ensure that tests of containment
sumps as required in this section are performed by qualified testers. The requirements for testers can be found in
20.5.105 NMAC.
I. Owners
and operators of storage tank systems shall dispose of water or other test
media used in testing of components of petroleum storage tank systems, or any
accumulated liquid with a visible sheen, and the disposal shall be in accordance
with all federal, state, and local statutes, ordinances, and regulations. Owners and operators who temporarily store
the test media or water on-site shall do so in accordance with all federal,
state, and local statutes, ordinances, and regulations.
[20.5.110.1007 NMAC - N,
07/24/2018]
20.5.110.1008 PERIODIC
OPERATION AND MAINTENANCE WALK-THROUGH INSPECTIONS:
A. Owners and
operators shall conduct walk-through inspections that, at a minimum, check
equipment as specified below:
(1) For
spill and overfill prevention equipment, every 30 days (exception: spill
prevention equipment at AST systems receiving deliveries at intervals greater
than every 30 days may be checked prior to each delivery):
(a) visually check
all spill and overfill prevention equipment for damage;
(b) remove liquid or debris;
(c) check for and remove obstructions
in the fill pipe;
(d) check the fill cap to make sure it is securely on
the fill pipe; and
(e) for double walled spill prevention equipment with interstitial monitoring, check for
liquid or a leak in the
interstitial area; and
(f) check
overfill prevention equipment for proper operation and determine whether
maintenance is required.
(2) For
release detection equipment, every 30 days:
(a) check
to make sure the release detection equipment
is operating with no alarms or
other unusual operating conditions present; and
(b) ensure records of release detection testing are reviewed and current.
(3) For
containment sumps, every 30 days:
(a) visually check
the containment sump for damage, liquid in the containment area, and
releases to the environment;
(b) remove
liquid and debris in
containment sumps; and
(c) for
double walled sumps with interstitial monitoring,
check for liquid or a leak in
the interstitial area.
(4) Annually: check hand held release detection equipment, such as, but not limited to, tank gauge sticks for operability and serviceability;
B. Owners
and operators shall conduct these walk-through inspections in accordance with
one of the following:
(1) the
current edition of a national code of practice or standard developed by a
nationally recognized association or independent testing laboratory that checks
equipment included in Subsection A of 20.5.110.1008 NMAC; or
(2) a
checklist developed by the department.
C. If monthly
visual checks of containment sumps are not being conducted or records of the
checks cannot be produced, a test in accordance with Subsection D of
20.5.10.1007 NMAC shall be conducted within 30 days of failing to meet the
requirement for monthly monitoring of the equipment.
D. Owners and operators must maintain
records of operation and
maintenance walkthrough inspections in accordance with 20.5.110.1015 NMAC. Records must include a list of each area checked, whether each area checked
was
acceptable or needed
action taken, a description of actions taken to correct
an issue, and delivery records if spill prevention
equipment is checked less frequently than every 30 days due
to infrequent deliveries.
[20.5.110.1008 NMAC - N,
07/24/2018]
20.5.110.1009 COMPATIBILITY: Owners and operators shall use a storage tank system made of or lined with materials that are compatible with the substance stored in the
storage tank system.
A. Owners
and operators must notify the department at least 30 days prior to changing the substance in any of
their tanks to a regulated substance
containing greater than ten percent ethanol, greater than twenty percent
biodiesel, or any other regulated substance identified by the department.
B. In addition,
owners and operators with storage tank systems storing
these regulated substances must meet one of the following:
(1) demonstrate
compatibility of the storage tank system
(including the tank, piping,
containment sumps, pumping equipment, release detection equipment, spill
equipment, and overfill equipment). Owners and operators may demonstrate
compatibility of the storage tank system by using one of the following options:
(a) certification or listing of storage
tank system equipment or components by a nationally recognized, independent
testing laboratory for use with the regulated substance stored; or
(b) equipment
or component manufacturer approval. The manufacturer’s approval must be in
writing, include an affirmative
statement of compatibility, specify the range
of biofuel blends the equipment or component is compatible with, and be from
the equipment or component manufacturer.
(2) for storage tank systems or system
components that contain, but are not compatible with, one of the regulated
substances listed in Subsection A of 20.5.110.1009 NMAC, or for those storage
tank systems where compatibility cannot be determined, remove all regulated
substances from the tank system by the effective date of these regulations, and
comply with one of the following:
(a) replace
the storage tank system or system components in accordance with the
requirements for a new storage tank system in 20.5.109 NMAC;
(b) prior
to putting the tank back in service, modify the storage tank system in
accordance with 20.5.110.1010 NMAC and one of the following:
(i) install
an internal lining in the tank, in accordance with the lining manufacturer’s
installation instructions, to address compatibility issues; or
(ii) comply
with tank or equipment manufacturer’s instructions;
(c) change
the regulated substance stored to one that is compatible with the storage tank
system; or
(d) permanently
close the storage tank system within 12 months of the effective date of these
regulations in accordance with the permanent closure requirements in
20.5.115.1502 NMAC; or
(3) use
another option determined by the department to be no less protective of human
health and the environment than the options listed in this section.
C. Owners
and operators must maintain records documenting compliance with this section
for as long as the storage tank system is used to store the regulated
substance.
D. Owners
and operators shall use the current
edition of an industry standard or code of practice developed by
a nationally recognized association or independent testing laboratory
approved in advance by the department
to comply with the compatibility requirements of this section. American
Petroleum Institute Recommended Practice RP 1626, “Storing and Handling Ethanol
and Gasoline-Ethanol Blends at Distribution Terminals and Filling Stations”
shall be used to comply with the requirements of this section as they pertain
to storage of ethanol blends.
[20.5.110.1009 NMAC - N,
07/24/2018]
20.5.110.1010 REPAIRS, REPLACEMENTS AND MODIFICATIONS: Owners and operators of a storage tank system
shall ensure that repairs, replacements, and modifications will prevent
releases due to structural failure or corrosion as long as the storage tank
system is used to store regulated substances.
Owners and operators shall remove all regulated substances from a
storage tank system when a release has been confirmed until it is repaired or
replaced in accordance with the requirements of this section.
A. Determining whether repair, replacement or modification
is necessary. Owners and operators shall
determine whether a repair, replacement or modification to a storage tank
system is necessary in consultation with a department inspector, after
providing notice required by this part.
(1) If owners and operators are
repairing, replacing or modifying piping of any kind that is connected to a
storage tank, the determination shall be made during an on-site inspection that
provides the inspector the opportunity to view the piping while it is exposed.
(2) If, during an on-site inspection, the
inspector determines that:
(a) any steel piping connected to a tank
indicates corrosion; or
(b) any non-corrodible piping connected
to a tank shows signs of deterioration or failure,
(3) Then the owner and operator shall
replace all piping connected to that tank, and shall inspect all other piping
at the same facility that is made of the same material to determine its
condition prior to returning the facility to operation.
B. Owners and operators shall properly
conduct repairs, replacements and modifications to storage tank systems in
accordance with the current edition of an industry standard or code of practice
developed by a nationally recognized association or independent testing
laboratory approved in advance by the department, and in accordance with the
manufacturer's instructions and recommended practices. Owners and operators shall use one or more of
the following to comply with the requirements of this section:
(1) National
Fire Protection Association Standard 30, “Flammable and Combustible Liquids
Code”;
(2) American
Petroleum Institute Recommended Practice RP 2200, “Repairing Crude Oil,
Liquefied Petroleum Gas, and Product Pipelines”;
(3) National
Fire Protection Association Standard 30A, “Code for Motor Fuel Dispensing
Facilities and Repair Garages”;
(4) Petroleum
Equipment Institute Publication RP200, “Recommended Practices for Installation
of Above Ground Storage Systems for Motor Vehicle Fueling”;
(5) American
Society for Testing and Materials ES40, “Emergency Standard Practice for
Alternative Procedures for the Assessment of Buried Steel Tanks Prior to the
Addition of Cathodic Protection”;
(6) American
Petroleum Institute 570, “Piping Inspection Code: Inspection, Repair,
Alteration and Rerating of In-Service Piping Systems”;
(7) American
Petroleum Institute Standard 653, “Tank Inspection, Repair, Alteration, and
Reconstruction”;
(8) American
Society of Mechanical Engineering Standard B31.1, “Process Piping”;
(9) International Code Council, “International
Fire Code”;
(10) National
Leak Prevention Association Publication RP823, “Standard for Preventative
Maintenance, Repair, and In-situ Construction of Petroleum Sumps”;
(11) Petroleum Equipment Institute Publication
RP100 “Recommended Practices for the Installation of Underground Storage Tank
Systems for Motor Vehicle Fueling”;
(12) Petroleum Equipment Institute Publication
RP800 “Recommended Practices for Installation of Bulk Storage Plants”;
(13) Petroleum Equipment Institute Publication
RP1000 “Recommended Practices for the Installation of Marina Fueling Systems”;
(14) Petroleum Equipment Institute Publication
RP1300 “Recommended Practices for the Design, Installation, Service, Repair,
and Maintenance of Aviation Fueling Systems”; or
(15) Petroleum Equipment Institute Publication RP1400
“Recommended Practices for the Design and Installation of Fueling Systems for
Emergency Generators, Stationary Diesel Engines and Oil Burner Systems”.
C. Owners and operators shall not internally line ASTs as a
means of repair.
D. Owners and operators shall tightness test a storage tank
system that has been
replaced, modified or repaired, prior
to returning the system to service, in accordance with 20.5.111.1101 NMAC and
Subparagraph (a) of Paragraph (3) of Subsection A of 20.5.111.1105 NMAC except
as provided below:
(1) the repaired or modified tank is
internally inspected in accordance with the current edition of an industry
standard or code of practice approved in advance by the department; or
(2) owners and operators shall use an
equivalent test method, which complies with the current edition of an industry
standard or code of practice developed by a nationally recognized association
or independent testing laboratory approved in advance in writing by the
department.
E. Upon completion of a modification or repair of any
cathodically protected storage tank system, owners and operators shall test the
cathodic protection system in accordance with 20.5.110.1006 NMAC to ensure that
it is operating properly.
F. Owners and operators of a storage tank system shall
maintain records of each repair, replacement and modification until the storage
tank system is permanently closed pursuant to 20.5.115 NMAC.
G. Owners and operators shall repair an above ground storage
tank if an internal inspection determines that a release is occurring or that
the tank bottom or shell thickness is below minimum thickness
requirements. Owners and operators shall
keep the records of internal inspections for the life of the tank. Minimum thickness requirements shall be determined
by one of the following:
(1) manufacturer’s specifications;
(2) current edition of an industry
standard or code of practice developed by a nationally recognized association or
independent testing laboratory approved in advance by the department; or
(3) minimum thickness for the tank bottom
shall never be less than one half of the original bottom plate thickness and
minimum thickness for the tank shall never be less than one-tenth inch.
H. Owners and operators shall meet all applicable
installation requirements of 20.5.109 NMAC, including testing requirements,
when repairing, replacing or modifying a storage tank system involves
installing new components. If any tank
or piping of a tank system is replaced, owners and operators shall follow all
requirements for properly assessing the site for contamination in compliance
with 20.5.115 NMAC prior to installing the new components.
I. Repairs to secondary containment
of tanks, piping and
containment sumps must be tested for
tightness according to the
manufacturer’s instructions,
a code of practice developed by a nationally recognized association
or independent testing laboratory,
or according to requirements established by the implementing agency within 30 days following the date of completion
of the repair.
J. Within 30 days following any repair
to spill or overfill prevention
equipment, the repaired spill or overfill prevention equipment must be tested
or inspected, as appropriate,
in accordance with 20.5.110.1005
NMAC to ensure it is operating properly.
[20.5.110.1010 NMAC - N,
07/24/2018]
20.5.110.1011 INSPECTIONS, MONITORING AND TESTING:
A. For the purpose of enforcing the provisions of these
regulations, all owners and operators of storage tanks shall, upon the request
of the secretary or authorized department representatives, furnish information
relating to such tanks, including tank equipment and contents, conduct
monitoring or testing, and permit any department representative at all
reasonable times to have access to, and to copy all records relating to such
tanks. Owners and operators shall comply
with all applicable and appropriate Occupational Health and Safety Act requirements,
Sections 50-9-1 through 50-9-25 NMSA 1978, so that storage tanks may be safely
inspected. For the purpose of enforcing
these regulations, department officers, employees, or representatives are
authorized to:
(1) enter at reasonable times any
establishment or place where a
storage tank is located;
(2) inspect the storage tank system and
obtain samples of its contents;
(3) conduct monitoring or testing of the
tanks, associated equipment, contents, or surrounding soils, air, surface
water, or groundwater; and
(4) retrieve all data from any electronic
release detection equipment or device.
B. The department shall commence and complete each
inspection with reasonable promptness.
If the secretary or department representative obtains any samples, prior
to leaving the premises he shall give to the owner, operator or agent in charge
a receipt describing the sample obtained and, if requested, a portion of each
sample equal in volume or weight to the portion retained. If any analysis is made of the samples, a
copy of the results of the analysis shall be furnished promptly to the owner,
operator or agent in charge.
C. Owners and operators shall permit the department or
authorized department representative to be present at and inspect all storage
tank system installations, replacements, repairs, substantial modifications,
installations of leak detection systems and storage tank system closures.
D. Owners and operators shall not intentionally delete any
history from any electronic release detection equipment or device.
[20.5.110.1011 NMAC - N,
07/24/2018]
20.5.110.1012 REQUIRED NOTIFICATION PRIOR TO
REPLACEMENT, REPAIR AND MODIFICATION:
To ensure that an inspector has an opportunity to be present during the
steps in procedures which are important to the prevention of releases, owners, operators,
and certified tank installers shall give the department notice of the dates on
which critical junctures in the replacement, repair, and modification of the
storage tank system are to take place. Notice need not be provided for normal
maintenance. The inspector may require that critical junctures be performed from
Monday through Friday during regular business hours.
A. For replacements, modifications (including internal
lining or changes to cathodic protection systems), and repairs, the term “critical
junctures” means:
(1) completion of pouring a concrete pad
or footings;
(2) completion of the excavation of
existing piping;
(3) actual performance of the repair,
lining, or modification;
(4) any time during the project in which
components of piping are connected;
(5) any time during the project in which
a tank, its associated piping, spill prevention equipment, or secondary
containment sumps are tested; and
(6) any time during the project when
overfill prevention equipment is inspected to ensure it meets the requirements
in 20.5.110.1005 NMAC.
B. Owners, operators and certified tank installers shall
give at least 30 days written notice before the replacement, modification or
repair of a storage tank system. Owners
and operators shall also give at least 30 days written notice before the
application of a secondary containment coating.
It may not be feasible for owners, operators, and certified tank
installers to provide advance notice of emergency repairs; however, owners,
operators, and certified tank installers shall provide notice of emergency
repairs as soon as possible after completing emergency repairs. At a minimum, the notice for replacements,
modifications, and repairs shall contain the following information:
(1) date the form is completed;
(2) facility name, facility ID number,
address (with county), and telephone number;
(3) owner name, owner ID number, address,
and telephone number;
(4) contractor name, address, and
telephone number;
(5) description of type of replacement,
modification or repair to be performed (such as spill containment, overfill
prevention, release detection, piping or other);
(6) expected date on which replacement,
modification or repair will be performed;
(7) whether any part of the system is
within 1,000 feet of a community water system or a potable drinking water well;
and
(8) signature of owner, operator or an
authorized representative.
C. In addition to the written notices described in this
section, owners, operators and certified tank installers shall give oral notice
at least 24 hours in advance of the commencement of the procedure. In the oral notice, owners, operators and
certified tank installers shall describe any changes to the 30-day written
notice required in Subsection B of this section, such as different equipment or
installation methods.
D. If
owners, operators and certified tank installers are separate persons, only one
person is required to comply with the notice requirements of this section;
however, all parties are liable in the event of noncompliance.
[20.5.110.1012 NMAC - N,
07/24/2018]
[The bureau provides an optional form
that may be used for notification of replacement, repair and modification. The
form is available on the petroleum storage tank bureau’s pages on the
department website or by contacting the Petroleum Storage Tank Bureau at
505-476-4397 or 2905 Rodeo Park Drive East, Santa Fe, NM 87505.]
20.5.110.1013 DEPARTMENT REVIEW AND APPROVAL OF
PLANS, INSTALLATION, OPERATION, AND MAINTENANCE: Owners and operators shall view any
inspection, review or approval by the department as permission to proceed in
accordance with all applicable rules, codes and standards. Review and approval by the department shall
not relieve any owner, operator, or certified tank installer of his
responsibility for compliance. If the
department overlooks any deficiencies or violations in the course of plan
review or inspection provided in 20.5 NMAC, the department may later require
correction and compliance.
[20.5.110.1013 NMAC - N, 07/24/2018]
20.5.110.1014 ALTERNATE METHODS:
A. If
owners and operators want to operate, maintain, replace, repair or modify any
part of a storage tank system with materials or methods that are not in accordance
with the current edition of an industry standard or code of practice developed
by a nationally recognized association or independent testing laboratory,
owners and operators shall apply in writing to the department, shall provide
supporting documentation, and shall not begin to operate, maintain, replace,
repair or modify the system, unless and until the department approves the
request in writing. At a minimum, the
request for an alternate method shall contain the following:
(1) date the form is completed;
(2) facility name, facility ID number,
address (with county) and telephone number;
(3) owner name, owner ID number, address
and telephone number;
(4) citation to regulation for which
alternate method or material (such as type of piping) is requested;
(5) brief description of the proposed
alternate method or material;
(6) justification of proposed alternate
method or material, including citation to a standard or code supporting its
use, if available; and
(7) demonstration of its equivalent
protection of public health, safety and welfare and the environment.
B. The
department shall not grant the request unless owners and operators demonstrate
that the request will provide equivalent protection of public health, safety
and welfare and the environment.
[20.5.110.1014 NMAC - N,
07/24/2018]
[The bureau provides an optional form
that may be used to request approval of an alternate
method. The
form is available on the petroleum storage tank bureau’s pages on the
department website or by contacting the Petroleum Storage Tank Bureau at
505-476-4397 or 2905 Rodeo Park Drive East, Building 1, Santa Fe, NM 87505.]
20.5.110.1015 RECORD KEEPING:
A. Owners and operators shall maintain the following
information for the life of the storage tank system:
(1) documentation
of operation of corrosion protection equipment that demonstrates compliance
with 20.5.110.1006 NMAC;
(2) documentation of storage tank system
repairs, replacements and modifications that demonstrate compliance with 20.5
NMAC;
(3) documentation of compliance with
release detection requirements in accordance with 20.5.11 NMAC;
(4) inspection logs required by 20.5.110
NMAC and 20.5.111 NMAC;
(5) tank tightness, internal inspection
and integrity test documents required by 20.5 NMAC;
(6) any document approving any alternate
method;
(7) spill and
overfill prevention equipment testing/inspection records;
(8) containment
sump testing records;
(9) documentation
of compatibility for AST systems;
(10) documentation of compliance for spill and overfill
prevention equipment and containment
sumps used for interstitial monitoring of piping;
(11) documentation of periodic
walkthroughs;
(12) documentation
of operator training in accordance with 20.5.104 NMAC;
(13) the operation and maintenance plan and
related documentation as required by 20.5.10.1001 NMAC; and
(14) any other record or written
approval required in 20.5 NMAC.
B. Availability and maintenance of records. Owners and operators shall keep the required
records for the operational life of a tank, piping and tank system either:
(1) at the storage tank site and
immediately available for inspection by the department; or
(2) at a readily available alternative
site and the records shall be provided for inspection to the department upon
request; if records are not available at a site during inspection, owners and
operators shall send to the inspector within 10 working days all records
requested by the inspector.
C. Owners and operators shall maintain permanent closure
records required under 20.5.115 NMAC. Owners and operators are also provided
with the additional alternative of mailing closure records to the department if
they cannot be kept at the site or an alternative site as indicated above.
D. If the owner and operator of a storage tank are separate
persons, only one person is required to comply with the requirements of this
section; however, both parties are liable in the event of noncompliance.
[20.5.110.1015 NMAC - N,
07/24/2018]
20.5.110.1016 REPORTING: Owners and
operators of a storage tank system shall cooperate fully with inspections,
monitoring and testing conducted by the department, as well as requests for
document submission, testing, and monitoring by the owner or operator.
A. Owners and operators shall provide the following
information to the department:
(1) registration for all storage tank
systems in accordance with 20.5.102 NMAC, which includes certification of
installation for new AST systems in accordance with Subsection C of 20.5.109.919
NMAC; (2) reports of all releases in accordance
with 20.5.102 NMAC and the requirements in 20.5.18 NMAC for reporting suspected
releases, spills and overfills and confirmed releases;
(3) corrective actions planned or taken
as required by 20.5.119 NMAC and 20.5.200 NMAC;
(4) notification before storage tank
system installation, replacement, repair or modification in accordance with
20.5.109 NMAC and 20.5.110 NMAC; notification when any person assumes ownership
of a storage tank system in accordance with 20.5.102 NMAC and notification
before permanent closure or change in service in accordance with 20.5.115 NMAC;
it may not be feasible for owners and operators to provide advance notice of
emergency repairs; however, owners and operators shall provide notice of
emergency repairs as soon as possible after completing emergency repairs;
(5) notification prior to storage tank
systems changing to certain regulated substances in accordance with Subsection
A of 20.5.110.1009 NMAC; and
(6) updated project drawings for any
addition, replacement or modification of a storage tank system.
B. Owners
and operators shall provide to the department all reports as required in
20.5.110 NMAC within 60 days of completion of the tests.
C. Owners
and operators shall report any failed tests or inspections to the department
within 24 hours of completion of the test or inspection in accordance with
20.5.118.1801 NMAC.
D. Owners
and operators shall ensure all reports required in 20.5.110 NMAC contain, at a
minimum, the following:
(1) facility
name and address;
(2) facility
ID number;
(3) owner
and operator name and address;
(4) owner
ID number;
(5) date
report was completed;
(6) date
of the test;
(7) duration
of the test;
(8) brand
name and model number of equipment being tested or sufficient description to
allow identification of the equipment;
(9) type
of equipment being tested;
(10) type
of test, including test procedures and methods;
(11) results
of the test;
(12) name
of the person who performed the inspection or test, and their qualifications as
specified in 20.5.105 NMAC;
(13) name
of the regulated substance stored in the tank associated with the equipment
being tested; and
(14) for
the inspections and testing of spill prevention equipment, overfill prevention
equipment, and containment sumps, include the information from the following
forms, as applicable, from Petroleum Equipment Institute Publication RP 1200, “Recommended
Practices for the Testing and
Verification of Spill, Overfill, Leak
Detection and Secondary Containment Equipment
at UST
Facilities”:
(a) “Spill Bucket Integrity Testing, Hydrostatic
Test Method, Single and Double-Walled Vacuum Method”;
(b) “Containment Sump Integrity Testing,
Hydrostatic Testing Method”;
(c) “UST Overfill Equipment Inspection,
Automatic Shutoff Device and Ball Float Valve”; or
(d) “Automatic Tank Gauge Operation Inspection”.
[20.5.110.1 NMAC - N,
07/24/2018]
HISTORY
OF 20.5.110 NMAC:
Pre-NMAC
History: The material in this part was derived
from that previously filed with the commission of public records - state
records center and archives.
EIB/USTR-5,
Underground Storage Tank Regulations-Part V-General Operating Requirements,
filed 9/12/88.
EIB/USTR-5,
Underground Storage Tank Regulations-Part V-General Operating Requirements,
filed 2/14/89.
EIB/USTR-5,
Underground Storage Tank Regulations-Part V-General Operating Requirements,
filed 8/4/89.
EIB/USTR-5,
Underground Storage Tank Regulations-Part V-General Operating Requirements,
filed 6/12/90.
History
of Repealed Material: 20 NMAC 5.5, Underground Storage
Tanks - General Operating Requirements (filed 2/27/97), repealed 8/15/03.
20.5.5
NMAC, Petroleum Storage Tanks, General Operating Requirements (filed 7/16/03)
repealed 4/4/08.
20.5.5
NMAC, Petroleum Storage Tanks, General Operating Requirements (filed 4/4/08)
repealed 7/24/18.
Other
History:
EIB/USTR-5, Underground Storage Tank
Regulations - Part V - General Operating Requirements, filed 6/12/90,
renumbered, reformatted and replaced by 20 NMAC 5.5, Underground Storage Tanks
- General Operating Requirements, effective 11/5/95;
20
NMAC 5.5, Underground Storage Tanks - General Operating Requirements filed
10/6/95 replaced by 20 NMAC 5.5, Underground Storage Tanks - General Operating
Requirements, effective 4/1/97;
20
NMAC 5.5, Underground Storage Tanks - General Operating Requirements, filed
2/27/97 was renumbered, reformatted and replaced by 20.5.5 NMAC, Petroleum
Storage Tanks, General Operating Requirements, effective 8/15/03.
20.5.5
NMAC, Petroleum Storage Tanks, General Operating Requirements (filed 7/16/03)
replaced by 20.5.5 NMAC, Petroleum Storage Tanks, General Operating
Requirements, effective 4/4/08.
20.5.5 NMAC, Petroleum Storage
Tanks, General Operating Requirements (filed 4/4/08) was renumbered,
reformatted, and replaced by 20.5.110 NMAC, Petroleum Storage Tanks, General
Operating Requirements for Above Ground Storage Tanks, effective 7/24/18.